Planned construction sequence and construction times
Expected construction period: December 2021 until end of 2023. Expected start date 13.12.2021
A large part of the measures can be implemented during ongoing operations either between or parallel to the events.
However, there are key measures that cannot be implemented between individual events.
The “lion’s share” of the key measures will therefore be able to be carried out in 2022, as the Congresshalle is to be closed for 6 months. (Closure from 03.06.2022) . After that, the remaining work is planned to be carried out in parallel with the event operations until the end of 2023, without having any disruptive effect on the events.